We continue to make excellent progress on our construction to date.
We remain focused on all critical path items in our effort to stick to our construction timeline to deliver the project, on budget, and on time in March 2021.
Our ownership team continues to meet every other Tuesday with our general contractor, Quasius, to continue to manage the construction process. These meetings will continue throughout construction until the units are delivered in March 2021.
The project continues to progress on schedule. The wood framing is at the 4th floor level with about 60% of the wall panels installed to date. The plumbing & heating contractors have begun to install their systems from the bottom floor and are working their way to the 4th floor. The mason has begun to install brick veneer on the south end of the building and will work its way around the building over the next several weeks to complete the install. All site utilities are installed. The roof is scheduled for a late August installation with windows to follow in early September.